GERC Rejects Plea to Extend Commissioning Time for 4 MW Solar Project
GERC Rejects Plea to Extend Commissioning Time for 4 MW Solar Project
AI 导读
The Commission found that the developer failed to establish force majeure as the cause of the commissioning delay November 5, 2026 Follow Mercom India on WhatsApp for exclusive updates on clean energy…